“A small roadway project consists of the following activities:”
| Activity | Duration (days) | Predecessor(s) |
|---|---|---|
| A | 4 | – |
| B | 6 | A |
| C | 3 | A |
| D | 5 | B, C |
| E | 2 | C |
| F | 4 | D, E |
“Determine the critical path and total project duration using the Critical Path Method (CPM).”
Step 1: Compute early start (ES) and early finish (EF) for each activity.
- A: ES = 0 → EF = 4
- B: ES = 4 → EF = 10
- C: ES = 4 → EF = 7
- D: ES = max(10, 7) = 10 → EF = 15
- E: ES = 7 → EF = 9
- F: ES = max(15, 9) = 15 → EF = 19
Step 2: Compute late finish (LF) and late start (LS).
- F: LF = 19 → LS = 15
- D: LF = 15 → LS = 10
- E: LF = 15 → LS = 13
- B: LF = 10 → LS = 4
- C: LF = min(10, 13) = 10 → LS = 7
- A: LF = min(4, 7) = 4 → LS = 0
Step 3: Identify the critical path (zero float).
Activities with zero float:
Answer: Critical Path = A–B–D–F; Total Project Duration = 19 days.