“A small roadway project consists of the following activities:”

ActivityDuration (days)Predecessor(s)
A4
B6A
C3A
D5B, C
E2C
F4D, E

“Determine the critical path and total project duration using the Critical Path Method (CPM).”

Step 1: Compute early start (ES) and early finish (EF) for each activity.

EF=ES+Duration

  • A: ES = 0 → EF = 4
  • B: ES = 4 → EF = 10
  • C: ES = 4 → EF = 7
  • D: ES = max(10, 7) = 10 → EF = 15
  • E: ES = 7 → EF = 9
  • F: ES = max(15, 9) = 15 → EF = 19

Step 2: Compute late finish (LF) and late start (LS).

LS=LFDuration

  • F: LF = 19 → LS = 15
  • D: LF = 15 → LS = 10
  • E: LF = 15 → LS = 13
  • B: LF = 10 → LS = 4
  • C: LF = min(10, 13) = 10 → LS = 7
  • A: LF = min(4, 7) = 4 → LS = 0

Step 3: Identify the critical path (zero float).

Activities with zero float: ABDF

Answer: Critical Path = A–B–D–F; Total Project Duration = 19 days.